Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
PRAKRITI SPARSH
|
BUILDING NO 1
|
31/12/2022
|
0
|
1
|
0
|
5
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 RK B WING |
18.65 |
3 |
3 |
2 |
1 BHK B WING |
27.38 |
3 |
1 |
3 |
1 BHK B WING |
27.91 |
3 |
3 |
4 |
2 BHK A WING |
39.55 |
6 |
0 |
5 |
1 RK |
19.41 |
3 |
2 |
6 |
2 BHK A WING |
42.05 |
3 |
3 |
7 |
1 BHK B WING |
31.16 |
3 |
2 |
8 |
2 BHK A WING |
40.62 |
4 |
2 |
9 |
2BHK |
42.92 |
2 |
0 |
10 |
2BHK |
43.99 |
1 |
0 |
11 |
1BHK |
31.98 |
1 |
0 |
12 |
1RK |
21.25 |
1 |
0 |
13 |
1RK |
23.11 |
1 |
0 |
14 |
1RK |
22.17 |
1 |
0 |
15 |
1RK |
22.51 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
PRAKRITI SPARSH
|
BUILDING NO 2
|
31/12/2022
|
0
|
1
|
0
|
4
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK A WING |
28.69 |
3 |
3 |
2 |
1 RK B WING |
17.44 |
3 |
3 |
3 |
1 BHK A WING |
27.57 |
3 |
2 |
4 |
1 BHK A WING |
28.42 |
3 |
2 |
5 |
1 BHK A WING |
27.03 |
3 |
3 |
6 |
1 BHK A WING |
27.38 |
3 |
1 |
7 |
1 BHK B WING |
29.72 |
3 |
2 |
8 |
1 BHK B WING |
29.37 |
3 |
2 |
9 |
1 BHK B WING |
27.27 |
3 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
PRAKRITI SPARSH
|
BUILDING NO 3
|
31/12/2022
|
0
|
1
|
0
|
5
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK |
29.44 |
3 |
2 |
2 |
2 BHK |
39.56 |
3 |
2 |
3 |
2 BHK |
41.7 |
3 |
3 |
4 |
1 BHK |
29.43 |
3 |
2 |
5 |
2BHK |
42.91 |
1 |
0 |
6 |
2BHK |
42.97 |
1 |
0 |
7 |
1BHK |
29.87 |
1 |
0 |
8 |
1BHK |
29.86 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
PRAKRITI SPARSH
|
BUILDING NO 4
|
31/12/2022
|
0
|
1
|
0
|
4
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK B WING |
28.58 |
3 |
1 |
2 |
1 RK A WING |
19.46 |
3 |
3 |
3 |
1 BHK A WING |
30.12 |
3 |
0 |
4 |
1 BHK B WING |
27.92 |
3 |
2 |
5 |
1 BHK B WING |
28.88 |
3 |
3 |
6 |
1 BHK B WING |
29.61 |
3 |
1 |
7 |
1 RK |
21 |
3 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
PRAKRITI SPARSH
|
BUILDING NO 5
|
31/12/2022
|
0
|
1
|
0
|
5
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK A WING |
28.42 |
3 |
2 |
2 |
1 BHK A WING |
27.6 |
3 |
1 |
3 |
1 BHK B WING |
29.8 |
3 |
2 |
4 |
1 BHK B WING |
27.69 |
3 |
1 |
5 |
1 BHK A WING |
27.69 |
3 |
1 |
6 |
1 BHK A WING |
27.37 |
3 |
2 |
7 |
1 RK A WING |
21.47 |
3 |
1 |
8 |
1 BHK B WING |
27.6 |
3 |
1 |
9 |
1 BHK B WING |
28.42 |
3 |
3 |
10 |
1 BHK B WING |
27.37 |
2 |
2 |
11 |
1 RK B WING |
27.37 |
1 |
1 |
12 |
1BHK |
30.6 |
2 |
0 |
13 |
1BHK |
30.24 |
2 |
0 |
14 |
1BHK |
31.14 |
2 |
0 |
15 |
1RK |
22.19 |
1 |
0 |
16 |
1RK |
22.55 |
2 |
0 |
17 |
1BHK |
29.8 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
PRAKRITI SPARSH
|
BUILDING NO 6
|
31/12/2022
|
0
|
1
|
0
|
5
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 BHK B WING |
44.22 |
3 |
0 |
2 |
2 BHK B WING |
44.85 |
3 |
1 |
3 |
1 BHK B WING |
29.45 |
3 |
0 |
4 |
1 BHK A WING |
29.31 |
3 |
1 |
5 |
1 BHK A WING |
27.19 |
6 |
2 |
6 |
1 BHK A WING |
28.15 |
3 |
1 |
7 |
1 BHK B WING |
26.76 |
3 |
3 |
8 |
1BHK |
32.22 |
1 |
0 |
9 |
1BHK |
30.31 |
1 |
0 |
10 |
1BHK |
30.47 |
1 |
0 |
11 |
1BHK |
31.53 |
1 |
0 |
12 |
1BHK |
32.35 |
1 |
0 |
13 |
1RK |
23.05 |
1 |
0 |
14 |
2BHK |
44.69 |
1 |
0 |
15 |
2BHK |
47.4 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|