MahaRERA Application

General Information

Other Than Individual

Organization

Shubham Homes and Contractors Pvt. Ltd.
Company
NA
Do you have any Past Experience ?
No

Address Details

303
Golden Bungalow
Juhu Road
Santacruz (W)
Near Santacruz West Police Station
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400054

Organization Contact Details

02226614503
www.shubhamgroup.net

Past Experience Details

Member Information

Member Name Designation Photo
Nimesh Subodh Dalal Partner View Photo
Dinesh Vinodchandra Shah Partner View Photo
Dinesh Vinodchandra Shah Authorized Signatory View Photo

Project

Shubham Trident - Sundew, Sunrise and Sunglow
On-Going Project
01/02/2021
30/12/2023
29/12/2024
No
Residential
No
1526 15261 to 2 1527 15271 to 4 1564 15641 to 4
CTS NO 1516-1529 -9-15 MTR WIDE DP ROAD
9-15 MTR WIDE DP ROAD - CTS NO 1563
13-40 MTR DP ROAD and CTS NO 1566 -
CTS NO 1528 - EXISTING ROAD
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
Ghatla Road
Chembur
400071
1651.80
3
3
0
170

FSI Details

4644.84
140
4784.84

Bank Details

HDFC Bank Limited
HDFC0000013

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 76 51 35

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 50 RAIN WATER HARVESTING
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 95 Almost done
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 ELECTRIC METER ROOMONLY
GYMNASIUM : YES 100 YET TO START
SOCIETY OFFICE : YES 100 YET TO START
Aggregate area of recreational Open Space : YES 50 YET TO START
Open Parking : NO 0 NA
Water Supply : YES 0 MCGM WATER SUPPLY
Sewerage (Chamber, Lines, Septic Tank , STP) : NO 0 NA
Storm Water Drains : YES 100 INTERNAL STORM WATER DRAIN IN PLOT
Landscaping & Tree Planting : YES 0 ONLY TREE PLANTING
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Shubham Trident - Sundew, Sunrise and Sunglow Sundew 30/12/2023 0 1 0 14 1 0 22
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 58.10 5 0
2 3BHK 87.66 1 0
3 2BHK 59.43 11 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 55
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Shubham Trident - Sundew, Sunrise and Sunglow Sunrise 30/12/2023 0 1 0 14 1 12 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.43 3 2
2 2BHK 55.75 2 0
3 4BHK 116.06 5 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 55
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Shubham Trident - Sundew, Sunrise and Sunglow Sunglow 30/12/2023 0 1 0 14 1 0 31
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 50.35 1 0
2 2BHK 51.1 14 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 73

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SK ENTERPRISE NA Contractor
KARANI & SANGHOI DESIGNERS NA Architect
Gireesh M.Rajadhyaksha Consulting Structural Engineers NA Engineer
REALTORS A51900004566 Real Estate Agent
RAHEJA ESTATE AGENCY A51800003110 Real Estate Agent
Rioga Premium Real Estate Advisory LLP A51800000974 Real Estate Agent
SUNIL RADHESHYAM SINGH A51800000987 Real Estate Agent
Furkhan I. Pettiwala NA Contractor
Chintan K. Shah NA Contractor
Ravi Sharoff NA Contractor
XTREME PROPERTIES A51800006795 Real Estate Agent
BHAVIN GIRISH SHAH A51800000647 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
8 Commencement Certificates / NA Order for plotted development
9 Commencement Certificates / NA Order for plotted development
10 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
2 CERSAI details
3 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
2 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement