MahaRERA Application

General Information

Individual

Individual

VINAYAK
KISHOR
GARVE
KISHOR SHNAKAR GARVE
Yes

Address For Official Communication

136/1A/6
Garve Motors
Mumbai-Banglore Highway
Wakad
Opp. Sayaji Hotel
MAHARASHTRA
Pune
Pune
Mulshi
Wakad
411057

Contact Details

02065112300

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SpringsOthersResidential and Commercial326562Kashid Park Pimple Gurav Pune 41106186/1/21912015-08-312015-08-18

Project

Golden Treasures Wing B
On-Going Project
18/04/2018
30/06/2018
30/06/2019
No
Residential
No
Survey No 19 Hissa No 1/4,Hissa No 1/5, Hissa No 1/6, Hissa No 1/7, Hissa No 1/8
Adjoining Survey No 18
Road
Adjoining Survey No 16
Adjoining Survey No 19 Part
MAHARASHTRA
Pune
Pune
Mulshi
Punawale
411057
3044.15
1
1
0
963.56

FSI Details

3437.86
0
3437.86

Bank Details

HDFC Bank
HDFC0000900

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 86 86 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Internal Roads in Tremix concrete and Footpaths
Water Conservation, Rain water Harvesting : YES 100 As per Drawings obtained from consultant
Energy management : YES 100 As per Drawings obtained from consultant
Fire Protection And Fire Safety Requirements : YES 100 As per Drawings obtained from consultant
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 As per Drawings obtained from consultant
Aggregate area of recreational Open Space : YES 100 Garden & Childrens Play Area
Open Parking : YES 100 Open & Visitors parking have been made.
Water Supply : YES 100 Water supply provision through Borewell and Tanker
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 As per Drawings obtained from consultant
Storm Water Drains : YES 100 As per Drawings obtained from consultant
Landscaping & Tree Planting : YES 100 As per Drawings obtained from consultant
Street Lighting : YES 100 As per Drawings obtained from consultant
Community Buildings : YES 100 Club House and Gym
Treatment And Disposal Of Sewage And Sullage Water : YES 100 As per Drawings obtained from consultant
Solid Waste Management And Disposal : YES 100 As per Drawings obtained from consultant

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Golden Treasures Wing B B 18/04/2018 0 1 1 13 0 0 86
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.56 11 11
2 1BHK 35.55 8 8
3 1BHK 35.71 24 24
4 1BHK 35.48 24 24
5 1BHK 35.33 19 19
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ABHIJIT SAHEBRAO SABBARWAR A52100000382 Real Estate Agent
Vitthal Marutirao Biradar NA Contractor
Milind Bhagwat Pokharkar NA Architect
Ganesh Balasaheb Deshmukh NA Engineer
Bipin Sharad Dorle NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement