MahaRERA Application

General Information

Other Than Individual

Organization

Cityscape Construction Co
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Nil
Meghdoot
Vallabh Baug Lane
Ghatkopar East
Damji Shamji Shah Chowk
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400077

Organization Contact Details

02221027711

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Mahavir Estella - C and D WingOthersResidential Cum Commercial773.26Near Sri Ram Hospital Mogarpada Village Ghodbunder Road Thane W - 400615S No 52 H No 1,2,3,42802016-09-302016-10-26
2Mahavir Exotica - A and B WingOthersResidential Cum Commercial2100Near Sri Ram Hospital Mogarpada Village Ghodbunder Road Thane W - 400615New S No 50, Hissa No 22682015-12-312016-02-16
3Mahavir Estella - Wing C and DOthersResidential cum commercial773.26Near Sri Ram Hospital Mogarpada Ghodbander Road Thane West - 400615S No 52 H No 1,2,3,42802016-09-302016-10-26
4Mahavir Estella - C and D WingOthersResidential cum Commercial773.26Near Sri Ram Hospital Mogarpada Village Ghodbunder Road Thane W - 400615S No 52 H No 1,2,3,42802016-09-302016-10-26

Member Information

Member Name Designation Photo
Pranay Shah Authorized Signatory View Photo

Project

Mahavir Estella - Wing A and B
On-Going Project
31/03/2017
31/12/2018
Yes
Residential
No
New S No 52, Hissa No 1,2,3,4
Building No 2 Wing C and D
Existing Road
Old S No 41 New S No 51
9 Meter wide Road
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400615
1605
1
1
0
0

FSI Details

2543.67
250
2793.67

Bank Details

ICICI Bank
ICIC0000026

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 20 0 70

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Work in progress
Water Conservation, Rain water Harvesting : YES 100 Yet to start
Energy management : YES 100 Part solar Completed.
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Electric meter room only.
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 100 Work Completed
Water Supply : YES 70 Work in progress
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Work Completed
Storm Water Drains : YES 100 Work Completed.
Landscaping & Tree Planting : YES 100 Only tree Planting.
Street Lighting : YES 100 Yet to start
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Mahavir Estella - Wing A and B Mahavir Estella Wing A and B 0 1 0 7 1 6 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop4 15.79 1 0
2 Shop6 22.67 1 0
3 Shop7 23.6 2 0
4 Shop8 24.43 1 0
5 Shop9 24.8 1 0
6 Shop10 25.64 1 0
7 Shop5 19.60 2 0
8 2BHK 48.68 47 17
9 Shop1 14.12 1 0
10 Shop2 14.31 1 0
11 Shop3 15.51 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 84

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Anil Hassanand Jagwani NA Architect
Akhil Agarwal NA Other Professional
Seed Reality NA Other Professional
PURBA JOSHI NA Other Professional
Elara Marketing NA Other Professional
DEEP PROPERTIES NA Other Professional
MOHAMMED AFFAN NA Other Professional
True World - HANUMAN TOSHNIWAL NA Other Professional
Sarvajeet Kaur NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Mahavir Estella - Wing A and B Court of Civil Judge SD Thane MCA No 234/2017 Civil No Suit NA 2017 Disposed
NA
Mahavir Estella - Wing A and B Court of the Civil Judge SD Thane SPECIAL CIVIL SUIT NO 719/2017 Civil No Suit NA 2017 The matter is kept for order of injunction application
NA
Mahavir Estella - Wing A and B Court of Civil Judge SD Thane 170 Civil No Suit NA 2014 Filing evidence of plaintiff
NA
Mahavir Estella - Wing A and B Court of Civil Judge SD Thane 61 Civil No Suit NA 2013 Disposed
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
6 Other
7 Other
8 Other
9 Other
10 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement