MahaRERA Application

General Information

Other Than Individual

Organization

ARP INFRA
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

204
DEVAVARATA BUILDING
SECTOR 17
VASHI
NEXT TO HDFC BANK
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227882888

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1URBAN VISTAOthersRESIDENTIAL + COMMERCIAL1128SURVEY NO.62 HISSA NO.5B-6 PLOT NO. 3-4-5 CHINCHAVLI SHEKIN TALUKA - KHALAPUR DISTRICT - RAIGAD KHOPOLI 4102031603/ 62/ PLOT 3,4,51392017-03-312017-02-04

Member Information

Member Name Designation Photo
BALRAJ BANSAL Partner View Photo
ARPIT BANSAL Partner View Photo
ARPIT BANSAL Authorized Signatory View Photo
BALRAJ BANSAL Authorized Signatory View Photo

Project

The Habitat
New Project
30/05/2023
No
Residential
No
Cts no. 1105Plot no. 2
open space
Cts 1105B
Cts 1106
Cts 1105 plot 1
MAHARASHTRA
Konkan
Raigarh
Khalapur
Khopoli
DP Road
Khopoli
410203
1232
1
1
0
0

FSI Details

2306.94
0
2306.94

Bank Details

hdfc bank
HDFC0000540

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 4 0 80

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 AFTER CONSTRUCTION
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AFTER CONSTRUCTION
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AFTER CONSTRUCTION
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 AFTER CONSTRUCTION
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AFTER CONSTRUCTION
Storm Water Drains : YES 100 AFTER CONSTRUCTION
Landscaping & Tree Planting : YES 100 AFTER CONSTRUCTION
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 AFTER CONSTRUCTION
Solid Waste Management And Disposal : YES 100 AFTER CONSTRUCTION

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 The Habitat THE HABITAT 30/05/2022 0 1 0 7 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 25.91 3 0
2 1 BHK 37.25 1 0
3 2 BHK 51.65 7 0
4 1 RK 20.71 42 18
5 2 BHK 49.42 6 1
6 1 BHK 30.75 6 4
7 1 BHK 33.90 6 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 83

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RAHUL SHIVKUMAR DUBEY A52000017780 Real Estate Agent
KHEMANT B TAILOR NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement