MahaRERA Application

General Information

Other Than Individual

Organization

ARIHANT SUPERSTRUCTURES LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

25TH FLOOR, B-WING
"ARIHANT AURA"
THANE BELAPUR ROAD
PLOT NO. 13/1, TTC INDUSTRIAL AREA
TURBHE
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02262493333

Past Experience Details

Member Information

Member Name Designation Photo
SAMEER GAJANAN GOLAPKAR Authorized Signatory View Photo

Project

ARIHANT AAYAN PHASE I
New Project
28/12/2030
No
Residential
Yes
Survey No 116 4,120 9,147 2/C, 147 2/D, 147 5, 147 6
Survey No 119 8
Survey No 147 5 and 147 2
Survey No 10 Survey No 116 3 and 116 2
Survey No 146 and road
MAHARASHTRA
Konkan
Thane
Kalyan
Titwala
Survey No 119
Titwala
421605
10660
1
1
0
1067.63

FSI Details

12004.26
4180.73
16184.99

Bank Details

ICICI Bank
ICIC0002841

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ARIHANT AAYAN PHASE I Ashokkumar B. Chhajer Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 16 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WNS
Water Conservation, Rain water Harvesting : YES 0 WNS
Energy management : YES 0 WNS
Fire Protection And Fire Safety Requirements : YES 0 WNS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WNS
Aggregate area of recreational Open Space : YES 0 WNS (Work in Progress)
Open Parking : YES 0 WNS
Water Supply : YES 0 WNS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WNS
Storm Water Drains : YES 0 WNS
Landscaping & Tree Planting : YES 0 WNS
Street Lighting : YES 0 WNS
Community Buildings : YES 0 WNS
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WNS
Solid Waste Management And Disposal : YES 0 WNS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARIHANT AAYAN PHASE I MABLE WING 28/12/2030 0 1 0 14 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.44 112 0
2 2BHK 48.53 1 0
3 2BHK 48.26 5 0
4 2BHK 47.48 1 0
5 2BHK 47.26 13 0
6 2BHK 46.13 78 0
7 Shop 18.42 1 0
8 Shop 18.42 1 0
9 Shop 24.46 1 0
10 Shop 16.08 1 0
11 Shop 18.43 1 0
12 Shop 16.08 1 0
13 Shop 26.13 1 0
14 Shop 16.08 1 0
15 Shop 18.42 1 0
16 Shop 22.11 1 0
17 Shop 18.42 1 0
18 Shop 16.08 1 0
19 Shop 26.13 1 0
20 Shop 16.08 1 0
21 Shop 18.43 1 0
22 Shop 22.11 1 0
23 Shop 18.42 1 0
24 Shop 16.08 1 0
25 Shop 26.13 1 0
26 Shop 16.08 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Yogita Bhandarkar NA Architect
Kaleem Sayyad NA Engineer
Anjani Goyal & Co NA Chartered Accountant
AMAN JYOTI DEKA A52000011060 Real Estate Agent
S. V. INCORPORATION A52000006542 Real Estate Agent
PROPWEB REALTY SERVICES PVT LTD A52000019540 Real Estate Agent
RISING HOMES A51700004600 Real Estate Agent
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
Global Homes A52000013825 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement