Project Details

Project Name:
Gingelia Residential
Promoter Name:
Acme Housing India Private Limited
Certificate Download:

Promoter Organization Name:

Sr. No. Name of Self-Regulatory Organization (SRO) Membership Number
1 CREDAI - MCHI (CREDAI - Maharashtra Chamber of Housing Industry) LM - C 196
2 NAREDCO (National Real Estate Development Council) F 064
3 BDA(Brihanmumbai Developers Association) SRON0144
District:
Thane
Registration Date:
25/07/2017
Proposed Date of Completion:
30/12/2023

Extension under Section 6:

Sr. No. From Date: To Date:
1st Extension 30/12/2022 30/12/2023

Extension under Section 7 (3):

Sr. No. From Date: To Date:
1st Extension NA NA

Building Details

Number of Apartment:
184
Number of Booked Apartment:
177
Percentage of Booked Apartment:
96.2

Form 5

Sr. No. Form 5 Document Upload Date View
1 Certificates of CA (Form 5) 30/09/2018
2 Certificates of CA (Form 5) 30/09/2019
3 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) 30/09/2020
4 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) 30/09/2020
5 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) 30/09/2021
6 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) 29/09/2022
7 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) 11/11/2022

Percentage of Work:

Sr. No. Building Name Percentage of Work (%)
1 Gingelia Residential 46.9

Complaint Details:

Sr. No. Complaint Number Date Appeal Filed
1 CC006000000056503 09/10/2018 No
2 CC006000000193980 18/11/2020 No
3 CC006000000198662 13/10/2021 No
Sr. No. Complaint Number Bench Name Roznama Roznama File Date
1 CC006000000056503 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Complainants present in person. Respondents Adv. Abir Patel a/w Adv. Shekhawat present. Respondents offered a cheque of refund to the complainant. Complainant saught time and requested for short date later on. Hence matter is adjourned to 22/01/19. NA 19/10/2018
2 CC006000000193980 CORAM: Hon'ble Shri. R P Deshpande, Member II, MahaRERA The Adv. for Respondent submitted that he need 1 week time to file the reply to the complaint filed by the Complainant. Considering the same time till 01.07.2024 is granted to the Respondent for filing the reply and thereafter, time till 08.07.2024 is granted to the Complainant to file rejoinder if any. This matter be scheduled on a suitable date after 08.07.2024 for argument. List this matter for hearing on 19.09.2024. 26/06/2024
3 CC006000000198662 CORAM: Hon'ble Shri. R P Deshpande, Member II, MahaRERA Considering the submission of both the parties the matter stands adjourned 08.07.2024. This matter be scheduled on a suitable date as early as possible for arguments after 08.07.2024. List this matter for hearing on 23.09.2024 26/06/2024
Sr. No. Complaint Number Interim Order Date
1 CC006000000056503 NA NA
2 CC006000000193980 NA NA
3 CC006000000198662 NA NA
Sr. No. Complaint Number Final Order Date
1 CC006000000056503 06/11/2020
2 CC006000000193980 NA NA
3 CC006000000198662 NA NA

Non Compliance Details:

Sr. No. Complaint Number Non Compliance Applied Date
1 CC006000000056503 NA
2 CC006000000193980 NA
3 CC006000000198662 NA
Sr. No. Complaint Number Non Compliance Roznama Roznama File Date
1 CC006000000056503 NA NA NA
2 CC006000000193980 NA NA NA
3 CC006000000198662 NA NA NA
Sr. No. Complaint Number Non Compliance Interim Order Date
1 CC006000000056503 NA NA
2 CC006000000193980 NA NA
3 CC006000000198662 NA NA
Sr. No. Complaint Number Non Compliance Final Order Date
1 CC006000000056503 NA NA
2 CC006000000193980 NA NA
3 CC006000000198662 NA NA

For Warrant Issued:

Sr. No. Complaint Number Warrant (Yes/No) Date of Issuance of Warrant District Collector Total Amount of Recovery Warrant Copy of Issued Warrant
1 CC006000000056503 No NA NA NA NA
2 CC006000000193980 No NA NA NA NA
3 CC006000000198662 No NA NA NA NA