CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present. The respondent has filed its reply to the complaint and written arguments as well. The complainant has filed its written arguments. Both the sides argued their case at length. The complainant desires refund with interest and compensation due to delay in completion of the project. The complainant also avers that the respondent never offered to sign the agreement for sale despite issuing allotment letter.
The respondent has refuted the contention of the complainant m
|
|
26/09/2022
|