Project Details

Project Name:
Aditya Enterprises
Promoter Name:
Aditya Enterprise
Certificate Download:

Promoter Organization Name:

Sr. No. Name of Self-Regulatory Organization (SRO) Membership Number
1 NA NA
District:
Mumbai Suburban
Registration Date:
09/08/2017
Proposed Date of Completion:
30/06/2021

Extension under Section 6:

Sr. No. From Date: To Date:
1st Extension NA NA

Extension under Section 7 (3):

Sr. No. From Date: To Date:
1st Extension NA NA

Building Details

Number of Apartment:
146
Number of Booked Apartment:
96
Percentage of Booked Apartment:
65.75

Form 5

Sr. No. Form 5 Document Upload Date View
1 Certificates of CA (Form 5) 27/12/2018
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) 24/06/2021

Percentage of Work:

Sr. No. Building Name Percentage of Work (%)
1 Audumbar Chhaya A2 79
2 AUDUMBAR CHHAYA A1 100

Complaint Details:

Sr. No. Complaint Number Date Appeal Filed
1 CC006000000141118 17/10/2019 No
Sr. No. Complaint Number Bench Name Roznama Roznama File Date
1 CC006000000141118 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Heard the complainant in person. None appeared for the respondent. In compliance to the principles of natural justice, the matter stands adjourned to 13/01/2020. NA 14/11/2019
Sr. No. Complaint Number Interim Order Date
1 CC006000000141118 NA NA
Sr. No. Complaint Number Final Order Date
1 CC006000000141118 20/01/2021

Non Compliance Details:

Sr. No. Complaint Number Non Compliance Applied Date
1 CC006000000141118 NA
Sr. No. Complaint Number Non Compliance Roznama Roznama File Date
1 CC006000000141118 NA NA NA
Sr. No. Complaint Number Non Compliance Interim Order Date
1 CC006000000141118 NA NA
Sr. No. Complaint Number Non Compliance Final Order Date
1 CC006000000141118 NA NA

For Warrant Issued:

Sr. No. Complaint Number Warrant (Yes/No) Date of Issuance of Warrant District Collector Total Amount of Recovery Warrant Copy of Issued Warrant
1 CC006000000141118 No NA NA NA NA