1
|
CC006000000302905
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
The complainant has prayed for refund in s.no.12 ( CC006000000302905 ) while the
complainant in s.no.15 ( CC006000000397128 ) has prayed for possession along with
interest and compensation for delay for a flat. The complainant at s.no.12 prays for
refund on the ground that third party rights have already been created in the said flat
by the respondent. A partial amount of Rs.13,26,000 has al
|
|
04/07/2024
|
2
|
CC006000000396832
|
CORAM: MumbaiBench7
|
Conciliation failed.
|
|
22/06/2024
|
3
|
CC006000000397128
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
The complainant has prayed for refund in s.no.12 ( CC006000000302905 ) while the
complainant in s.no.15 ( CC006000000397128 ) has prayed for possession along with
interest and compensation for delay for a flat. The complainant at s.no.12 prays for
refund on the ground that third party rights have already been created in the said flat
by the respondent. A partial amount of Rs.13,26,000 has al
|
|
04/07/2024
|
4
|
CC006000000397790
|
CORAM: MumbaiBench7
|
The matter is adjourned till next date.
|
|
26/06/2024
|