Project Details

Project Name:
BOBE Chandralekha CHSL
Promoter Name:
Ssakash Developers & Builders Pvt Ltd
Certificate Download:

Promoter Organization Name:

Sr. No. Name of Self-Regulatory Organization (SRO) Membership Number
1 NA NA
District:
Mumbai Suburban
Registration Date:
14/09/2017
Proposed Date of Completion:
30/12/2021

Extension under Section 6:

Sr. No. From Date: To Date:
1st Extension NA NA

Extension under Section 7 (3):

Sr. No. From Date: To Date:
1st Extension 31/12/2019 31/12/2020

Building Details

Number of Apartment:
108
Number of Booked Apartment:
108
Percentage of Booked Apartment:
100

Form 5

Sr. No. Form 5 Document Upload Date View
1 NA NA NA

Percentage of Work:

Sr. No. Building Name Percentage of Work (%)
1 B 81.1
2 A 63

Complaint Details:

Sr. No. Complaint Number Date Appeal Filed
1 CC006000000078953 18/04/2019 Yes
2 CC006000000089927 02/07/2019 Yes
3 CC006000000193976 10/09/2020 No
4 CC006000000193988 11/09/2020 No
5 CC006000000196083 20/02/2021 No
Sr. No. Complaint Number Bench Name Roznama Roznama File Date
1 CC006000000078953 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA S parthasarathy for complainant Niraj for the respondent. AAdj to 23/10/19 NA 28/07/2019
2 CC006000000089927 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Adv. Nimky Nagda appeared for the complainant. Mr. Niraj Pandey appeared for the respondent. Respondent to file reply within 2 weeks. Matter adjourned to 02/12/2019. NA 01/08/2019
3 CC006000000193976 CORAM: Hon’ble Shri. Ajoy Mehta, Chairperson, MahaRERA 15/04/2021 17/03/2021
4 CC006000000193988 CORAM: Hon’ble Shri. Ajoy Mehta, Chairperson, MahaRERA The Complainant is present; the Respondent is absent. The Complainant states that the matter is amicably settled before the conciliation forum and he seeks to withdraw. The matter stands disposed as withdrawn with consent terms on record. 02/09/2022
5 CC006000000196083 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA The complainant could not heard be heard due to technical problem. The respondent to file reply within a week period. The case stands adjourned till 15th April 2021. 30/03/2021
Sr. No. Complaint Number Interim Order Date
1 CC006000000078953 NA NA
2 CC006000000089927 NA NA
3 CC006000000193976 NA NA
4 CC006000000193988 NA NA
5 CC006000000196083 NA NA
Sr. No. Complaint Number Final Order Date
1 CC006000000078953 11/01/2020
2 CC006000000089927 06/12/2019
3 CC006000000193976 16/04/2021
4 CC006000000193988 02/09/2022
5 CC006000000196083 NA NA

Non Compliance Details:

Sr. No. Complaint Number Non Compliance Applied Date
1 CC006000000078953 NA
2 CC006000000089927 21/08/2023
3 CC006000000089927 12/05/2022
4 CC006000000193976 NA
5 CC006000000193988 NA
6 CC006000000196083 NA
Sr. No. Complaint Number Non Compliance Roznama Roznama File Date
1 CC006000000078953 NA NA NA
2 CC006000000089927 The matter is called out repeatedly. None appeared for any of the parties in spite of the link sent. The matter is adjourned to 02.09.2024 @ 12 noon. 06/08/2024
3 CC006000000193976 NA NA NA
4 CC006000000193988 NA NA NA
5 CC006000000196083 NA NA NA
Sr. No. Complaint Number Non Compliance Interim Order Date
1 CC006000000078953 NA NA
2 CC006000000089927 NA NA
3 CC006000000193976 NA NA
4 CC006000000193988 NA NA
5 CC006000000196083 NA NA
Sr. No. Complaint Number Non Compliance Final Order Date
1 CC006000000078953 NA NA
2 CC006000000089927 17/10/2023
3 CC006000000193976 NA NA
4 CC006000000193988 NA NA
5 CC006000000196083 NA NA

For Warrant Issued:

Sr. No. Complaint Number Warrant (Yes/No) Date of Issuance of Warrant District Collector Total Amount of Recovery Warrant Copy of Issued Warrant
1 CC006000000078953 No NA NA NA NA
2 CC006000000089927 No NA NA NA NA
3 CC006000000193976 No NA NA NA NA
4 CC006000000193988 No NA NA NA NA
5 CC006000000196083 No NA NA NA NA