Project Details

Project Name:
Xrbia Vangani Ph 2
Promoter Name:
Xrbia Developers Ltd
Certificate Download:

Promoter Organization Name:

Sr. No. Name of Self-Regulatory Organization (SRO) Membership Number
1 CREDAI MAHARASHTRA (Confederation of Real Estate Developers Associations of India) CREDAI-PM/08-09/318
District:
Raigarh
Registration Date:
22/08/2017
Proposed Date of Completion:
30/03/2025

Extension under Section 6:

Sr. No. From Date: To Date:
1st Extension NA NA

Extension under Section 7 (3):

Sr. No. From Date: To Date:
1st Extension NA NA

Building Details

Number of Apartment:
1536
Number of Booked Apartment:
365
Percentage of Booked Apartment:
23.76

Form 5

Sr. No. Form 5 Document Upload Date View
1 Certificates of CA (Form 5) 03/11/2018
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) 30/12/2019
3 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) 28/05/2021
4 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) 25/01/2023
5 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) 03/08/2023

Percentage of Work:

Sr. No. Building Name Percentage of Work (%)
1 A2 26.3
2 B4 0
3 C10 10
4 C7 0
5 C8 10
6 C9 10
7 D5 0
8 H1 0
9 L1 10
10 M2 28.3

Complaint Details:

Sr. No. Complaint Number Date Appeal Filed
1 CC006000000192838 04/03/2020 No
2 CC006000000193080 20/03/2020 No
3 CC006000000197370 29/06/2021 No
Sr. No. Complaint Number Bench Name Roznama Roznama File Date
1 CC006000000192838 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Complainant absent. Respondent present. The learned advocate for the respondent submitted that the parties have settled the matter amicably before MahaRERA Conciliation Forum. Hence, the complaint stands disposed of as settled. 30/10/2021
2 CC006000000193080 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA The complainant present. Respondent absent. Heard the arguments of the complainant. Order is reserved. 24/11/2021
3 CC006000000197370 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA The respondent is heard. The complainant is absent. The learned advocate for the respondent stated that the parties have settled the matter amicably before the MahaRERA Conciliation Forum. The same is recorded in the roznama of Conciliation Forum. In view of the above, since the parties have settled the matter, nothing survives in the complaint. Consequently, the complaint stands disposed of as settled. 02/06/2022
Sr. No. Complaint Number Interim Order Date
1 CC006000000192838 NA NA
2 CC006000000193080 NA NA
3 CC006000000197370 NA NA
Sr. No. Complaint Number Final Order Date
1 CC006000000192838 30/10/2021
2 CC006000000193080 28/02/2022
3 CC006000000197370 02/06/2022

Non Compliance Details:

Sr. No. Complaint Number Non Compliance Applied Date
1 CC006000000192838 NA
2 CC006000000193080 11/05/2022
3 CC006000000197370 NA
Sr. No. Complaint Number Non Compliance Roznama Roznama File Date
1 CC006000000192838 NA NA NA
2 CC006000000193080 Complainant present but respondent absent. None present for the respondent. According to complainant vide order dated 22-2-2022 directed the respondent for refund of amount together with interest, but till date the said order is not complied by the respondent and hence prayed for stringent action. None present for the respondent and hence submission on behalf of respondent not on record. Vide order dated 22-2-2022 passed by Hon’ble Member-I, MahaRERA directed to respondent to refund the e 06/06/2023
3 CC006000000197370 NA NA NA
Sr. No. Complaint Number Non Compliance Interim Order Date
1 CC006000000192838 NA NA
2 CC006000000193080 NA NA
3 CC006000000197370 NA NA
Sr. No. Complaint Number Non Compliance Final Order Date
1 CC006000000192838 NA NA
2 CC006000000193080 06/06/2023
3 CC006000000197370 NA NA

For Warrant Issued:

Sr. No. Complaint Number Warrant (Yes/No) Date of Issuance of Warrant District Collector Total Amount of Recovery Warrant Copy of Issued Warrant
1 CC006000000192838 No NA NA NA NA
2 CC006000000193080 Yes 11/01/2024 Raigad 391248.00
3 CC006000000197370 No NA NA NA NA