Sr. No.
|
Complaint Number
|
Bench Name
|
Roznama
|
Roznama File
|
Date
|
1
|
CC005000000177929
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
The present complaint is filed by the complainant claiming to be one of the
landowners in the project land for which the respondent has signed Development
Agreement in November 2022. The complainant has already filed a Regular Civil Suit
No. 1042 of 2022 in the Civil Court at Pune which is also mentioned in the pending
litigation column of the project registration. Therefore, the respondent has raised 2
issues that i) the complaint is not legible ii) it is als
|
|
01/08/2024
|
2
|
CC005000000177936
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
The respondent has filed its reply to the complaint on 27-02-2023 and has provided the
facts of the case along with all the necessary documents. The complainant applied for
a flat vide booking application form dated 19-11-2022. However, due to certain
reasons the respondent refunded the said amount on 09-12-2022, according to the
respondent, which was paid to the complainant on 14-12-2022, on which date the
complainant has filed this complaint. The complainant
|
|
01/08/2024
|
3
|
CC005000000269416
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
“Conciliation Successful matter”
Both the parties are present.
Both the parties confirm that the matter is amicably settled on 25-11-2023 before the
MahaRERA Conciliation Forum. Accordingly, the Conciliation Forum has referred the
matter to MahaRERA as a conciliation successful matter on 20-12-2023.
In view of the above, this matter is disposed of as settled as per the terms of
conciliation.
|
|
29/12/2023
|