1
|
CC006000000196545
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
Both the parties have argued their matter today. The complainant has prayed for
interest and compensation for the delay as the project was to be completed in March
2014, according to the agreement for sale of October 2013. However, the project is still
incomplete and the respondent has contended that it is likely to be completed soon.
The respondent has pointed out the reasons for the delay contending that the project
fell in the ‘Green Zone’ because of which
|
|
01/08/2023
|
2
|
CC006000000197794
|
CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA
|
Both the parties are present.
Admittedly, there is a delay in completion of the project as it was to be completed in
June 2014 as per the agreement for sale, however, because of the issue of forest
clearance, the project has been delayed. The respondent has filed its reply to the
amendment application of the complainant as the complainant has changed his
prayers of “possession along with interest and compensation” to “refund along with
interest and compensation for the delay”. The responde
|
|
03/03/2023
|