Project Details

Project Name:
VIVA VISHNUPURAM -ARCHIT
Promoter Name:
VIVA HOMES PRIVATE LIMITED
Certificate Download:

Promoter Organization Name:

Sr. No. Name of Self-Regulatory Organization (SRO) Membership Number
1 NAREDCO (National Real Estate Development Council) R/141
District:
Palghar
Registration Date:
17/08/2017
Proposed Date of Completion:
30/12/2025

Extension under Section 6:

Sr. No. From Date: To Date:
1st Extension 30/06/2021 30/06/2022

Extension under Section 7 (3):

Sr. No. From Date: To Date:
1st Extension 30/06/2022 30/12/2023
2nd Extension 30/12/2023 30/12/2024
3rd Extension 30/12/2024 30/12/2025

Building Details

Number of Apartment:
58
Number of Booked Apartment:
46
Percentage of Booked Apartment:
79.31

Form 5

Sr. No. Form 5 Document Upload Date View
1 Certificates of CA (Form 5) 16/05/2019
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) 26/06/2021
3 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) 29/06/2021
4 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) 29/06/2021
5 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) 29/12/2022
6 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) 15/12/2023
7 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) 19/12/2024

Percentage of Work:

Sr. No. Building Name Percentage of Work (%)
1 ARCHIT 58

Complaint Details:

Sr. No. Complaint Number Date Appeal Filed
1 CC006000000196545 01/04/2021 No
2 CC006000000197794 04/09/2021 No
Sr. No. Complaint Number Bench Name Roznama Roznama File Date
1 CC006000000196545 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Both the parties are present. Both the parties have argued their matter today. The complainant has prayed for interest and compensation for the delay as the project was to be completed in March 2014, according to the agreement for sale of October 2013. However, the project is still incomplete and the respondent has contended that it is likely to be completed soon. The respondent has pointed out the reasons for the delay contending that the project fell in the ‘Green Zone’ because of which 01/08/2023
2 CC006000000197794 CORAM: Hon’ble Shri. Mahesh Pathak, Member I, MahaRERA Both the parties are present. Admittedly, there is a delay in completion of the project as it was to be completed in June 2014 as per the agreement for sale, however, because of the issue of forest clearance, the project has been delayed. The respondent has filed its reply to the amendment application of the complainant as the complainant has changed his prayers of “possession along with interest and compensation” to “refund along with interest and compensation for the delay”. The responde 03/03/2023
Sr. No. Complaint Number Interim Order Date
1 CC006000000196545 NA NA
2 CC006000000197794 NA NA
Sr. No. Complaint Number Final Order Date
1 CC006000000196545 15/01/2024
2 CC006000000197794 18/07/2023

Non Compliance Details:

Sr. No. Complaint Number Non Compliance Applied Date
1 CC006000000196545 NA
2 CC006000000197794 14/03/2024
Sr. No. Complaint Number Non Compliance Roznama Roznama File Date
1 CC006000000196545 NA NA NA
2 CC006000000197794 Adv. Prasad Keluskar for the complainant present. Mr. Anup Mehta, A.R. for the respondent present. Heard arguments of both the parties. Reserved for order. 23/04/2024
Sr. No. Complaint Number Non Compliance Interim Order Date
1 CC006000000196545 NA NA
2 CC006000000197794 NA NA
Sr. No. Complaint Number Non Compliance Final Order Date
1 CC006000000196545 NA NA
2 CC006000000197794 19/06/2024

For Warrant Issued:

Sr. No. Complaint Number Warrant (Yes/No) Date of Issuance of Warrant District Collector Total Amount of Recovery Warrant Copy of Issued Warrant
1 CC006000000196545 No NA NA NA NA
2 CC006000000197794 No NA NA NA NA